Abstract: Effort estimation
using Use Case Point (UCP) method obtained from the multiplication of the UCP
with the Effort Rate (ER). Some studies conclude that there is some value of ER
used in the calculation of effort estimation. However, the most often used is
the ER with value 20 man-hours given by Karner. Disputes about the research
that is ER by Karner occurred in 1993, so it is possible that the ER by Karner
not suitable when applied in the calculation of effort estimation for the
project worked on in 2013 and the years to come.
This study used 8 data of governance website software development
projects. The data is used to calculate actual effort, making use case
diagrams, and calculations UCP estimation. Further level of analysis that is
performed correlation and regression equations for actual effort and the UCP
estimation. Based on the regression equation then performed calculations
tangent ? to produce the ER.
From this research produced the ER as big as 5,178 man-hours. The ER is
much smaller than the value given by Karner ER. Case is possible for several
reasons, among others: 1) Enginering software technology that is growing
rapidly. 2) Manufacturing website using components. 3) Source of the internet
so complete.
Penulis: Wahyu Kurniawan,
Sholiq Sholiq, Teguh Sutanto
Kode Jurnal: jptkomputerdd130198