PARAMETRIC STUDY FACTORS AFFECTING PROJECT MANAGEMANT OF CONSTRUCTION IN SOUTH LIBYA
Abstract: Unexpected delays in construction projects
are caused by owner,contractor, or a third party in which several types of
delays may occurconcurrently. The effect
of delays does not only influence the construction industry but the overall
economy as well. As such, the objectives of the presented research in this
paper are to identify, study, the factors that caused the delay in project duration.
Simulation-based Analytic Hierarchy Process (AHP). Were collected the data from
owner and companies in Ghat, Libya. The model is implemented to the collected
data, which show robust results. Based upon collected the data for the project
of 3000 Houses in Ghat. The priorities according to the analysis of
hierarchical (AHP) are from the questioners, the most important in this problem
of project is Management conditions ranked first at 0.470. The next is Project
conditions ranked 0.370 the last Environmental conditions ranked at 0.160.This
result is to the real case study of project. In management the result problem,
payment delay and Time to make Decision and productivity uncertainty of labor
is big problem from management condition. The Project conditions are the second
problem from the project. In project conditions the result problem, material
availability is biggest problem from project condition. The environmental
condition is the third problem from the project. In environmental conditions
the result problem, labor strike and shortage of human resources is largest
problem from environmental conditions.
Author: Alsadik Mohmed Ali
Akoni
Journal Code: jptsipilgg140014