PENJADWALAN MESIN SCREW PRESS STASIUN KEMPA PADA PRODUKSI CPO (CRUDE PALM OIL) DAN KERNEL DENGAN MENGGUNAKAN METODE INDIKATOR
Abstract: Complex problems
often encountered in the company, especially the production. The company should
be able to increase production capability by increasing the utility of existing
resources and accuracy in the completion of production to match the deadlines
set by scheduling planned well. As a company produces CPO and kernel
continuously so the scheduling screw press machine should be well planned so
that production can be completed on time, damage to the engine and overtime can
be avoided. This study aims to analyze the utilization schedule and screw press
machine at the station felt that optimal production can be achieved and
determine the cause of the delay production time resulting in overtime. The
method used is the method of indicators that can be applied to the machine
which is parallel with different capacities. This method minimizes the
turnaround time by prioritizing machine with a large capacity while maintaining
the efficiency of the engine and the completion time has been determined.
Proposed scheduling using indicators generate optimal schedule, 13840 hours of
work available only used 12373.5 hours with five machine screw press, the clock
difference is 1408.5 hours of work hours are unemployed and 58 hours of
treatment machine screw press, and produce five utilities screw press machine
on average up to 89.40% and utilities average every month five screw press
machine is 89.46%. The delay time of CPO production process and the kernel has
been caused by damage to machine screw press which occur during the production
process takes place so that if the production capacity is reduced and overtime
hours cannot be avoided. Screw press machine maintenance can be done by the
engine maintenance schedule time without having to wait for the machine was
broken beforehand and this can reduce the cost of production.
Penulis: Heri Wibowo
Kode Jurnal: jptindustridd160033