EVALUASI DAN PERENCANAAN MITIGASI RESIKO PROYEK PEMBANGUNAN JALUR GANDA KERETA API SEMARANG - BOJONEGORO
Abstract: Calista Perkasa
Mulia ( CPM ) ltd is a contracting company of the railway construction. In the
project construction of double track railway Semarang- Bojonegoro period April
2012 to December 2013 , scheduling and risk management has not been implemented
properly. It could been seen from the works that was not completed on schedule.
Therefore, the purpose of this study was to design a project scheduling with
precedence diagram method (PDM) and risk management. The results showed that
one of the strategies which could be applied to anticipate the delay was the
acceleration of the project. With this strategy the project could save as much
as Rp730.638.742. Furthermore the risk of sources showed there were 28.21 % of
technical risks, 46.15 % of not expected risk and 33.33 % unacceptable risk.
Penulis: Aswan Munang, Faisal
RM, Agus Mansur
Kode Jurnal: jptindustridd160142