Pengelolaan Supply Produk Waferstick dengan Mempertimbangkan Kapasitas Produksi dan Persediaan Barang Jadi di PT. Tiga Pilar Sejahtera Food,Tbk
Abstract: In general, planning
supply use the information from combination varying capacity and inventory to
plan the aggregate rates of production by time period for groups of product.
This research objective is PT. Tiga Pilar Sejahtera’s (TPS) that produces wafersticks.
In the company sometimes occured the wafersticks product can be not fulfilled.
This is happened because waferstick inventory unstable. This causes problems
that PT. Tiga Pilar Sejahtera (TPS) was less capable to fulfill the market’s
demands. To solve this PT TPS should be managing the working hours, workforces,
production capacity and finished goods inventory, they are called aggregate
planning. This research are determine safety stocks, planning supply and
material inventory planning.Managing supply of waferstick product is started by
forecast the demand. The forecast result is used to estimate safety stock of
waferstick. Then the forecasting result and safety stock become of input
Integer linier programming model to determine aggregate planning. The aggregate
planning is used to find optomal lot size of waferstick raw material. Then lot
sizing become input Planned Order Receipt in the Material Planning Requirements
(MRP). Forecast method used to forecast the demand is decomposition, this
method is he best method find estimation demand because it have more less MAD
than the other. The determination of the safety stock is actually more accurate
with the 90% by Romy & Yuli waferstick safety inventory is 1106 cartons and
2364 cartons for Pio. From aggregate planning there is back order in 13 th is
11 cartons. The planning cost for Romy & Yuli waferstick Rp 625.670.902,33
and Cost for Pio waferstick Rp 1.462.296.180,00. Waferstick material planning
by optimal lot size between 695 kilograms up to 8487 kilograms by waferstick
materials cost is Rp 6.315.520,00.
Keywords: The aggregate
planning; safety stock; Material Requirement Planning (MRP); Production
Planning
Penulis: Yuniaristanto, Azizah
Aisyati, Tri Hariyanto
Kode Jurnal: jptindustridd070048

Artikel Terkait :
Jp Teknik Industri dd 2007
- Pengaruh Pemasangan Kapasitor Shunt Terhadap Konsumsi Daya Aktif Instalasi Listrik
- Perancangan Aplikasi Informasi SMS untuk Alumni Unsoed Menggunakan UML (Unified Modeling Language)
- Initial Tuning Sebagai Salah Satu Metode Pengoptimalan New Site Pada Jaringan Seluler Gsm (Studi Kasus Pada Area Kerja Pt. Sinergi Telecom Under Ericsson Network)
- Peningkatan Efesiensi Produksi Electric Arc Furnace Dengan Injeksi Oksigen Untuk Menghemat Biaya Energi Listrik Pada Industri Baja
- Prediksi Penyakit Demam Berdarah Dengue (Dbd) Dan Tifus Menggunakan Jaringan Syaraf Tiruan Perambatan Balik (Back Propagation)
- Perencanaan Sistem Distribusi Dengan Analisa Aliran Daya
- Kajian Unjuk Kerja Metode Hidrograf Satuan Sintetik Untuk Penetapan Banjir Rancangan Pada Das Di Pulau Jawa (Studi Kasus Das Cimanuk Hulu)
- IDENTIFIKASI LOKASI STRATEGIS UNTUK KAWASAN INDUSTRI DI KABUPATEN PURBALINGGA
- PROFIL MUKA AIR DI HULU GROUNDSILL TIPE AMBANG LEBAR DAN OGEE
- PEMBATAS KECEPATAN DATA PADA PC-ROUTER BERBASIS LINUX MENGGUNAKAN DISIPLIN ANTRIAN HIERARCHICAL TOKEN BUCKET (HTB)
- SEPTICTANK PERESAPAN SISTEM KANAL (PERSIKAN) SEBAGAI TEKNOLOGI ALTERNATIF PENGENDALIAN PENCEMARAN KOLIFORM TINJA PADA PEMUKIMAN PADAT
- STUDI PENDAHULUAN GEOLOGI GUA LAWA DI PURBALINGGA, JAWA TENGAH
- PENGARUH PENGGUNAAN VISCOCRETE-10 DAN SERAT BAN BEKAS TERHADAP NILAI SLUMP DAN KUAT TEKAN BETON SERAT
- Peningkatan Pelayanan Jasa dengan Menggunakan Metode Servqual dan Metode Quality Function Deployment (Studi Kasus di Larissa Skin Care and Hair Treatment, Surakarta)
- Pengembangan Model untuk Memprediksi Kontribusi Ekonomi dari Kunjungan Wisatawan
- Perencanaan Pengambilan Sampel Lampu TL Dop 10 W pada Post Quality Inspection dengan Metode Military Standard 105D di PT. General Electric Lighting Indonesia
- Evaluasi Proses Pembelajaran Berdasarkan pada Voice Of Customer (Studi Kasus pada Fakultas X, Universitas Y)
- Penjadwalan Batch Dinamis Flow Shop Untuk Meminimasi Rata-Rata Keterlambatan Penyelesaian Order (Mean Tardiness) dan Jumlah Scrap Tuang di CV. Kembar Jaya
- Analisa Faktor-Faktor yang Mempengaruhi Konsumen dalam Keputusan Pembelian Mobil Toyota di Surakarta
- Perbaikan Proses Bisnis Pasang Baru Telepon Kabel di Wilayah Pemasangan Baru Surakarta dengan Metode Fault Tree Analysis
- Pengembangan Model Persediaan Single Vendor-Single Buyer dengan Lead Time Dapat Dikontrol
- Perancangan Sistem Pendukung Keputusan Pengendalian Persediaan Obat Gawat Darurat Prioritas I di RSUD Dr. Moewardi Surakarta
- Penentuan Rute Dan Jadwal Pengiriman Galon Air Minum Dalam Kemasan (AMDK) Dengan Menggunakan Metode Clark And Wright Saving Heuristic
- Perancangan Sistem Informasi Pemrosesan Order Produk Ortosa Prostesa Di Instalasi Ortotik Prostetik Rumah Sakit Ortopedi Prof.Dr. R. Soeharso Surakarta