PENJADWALAN FLOW SHOP DENGAN PENDEKATAN CROSS ENTROPY-GENETIC ALGORITHM UNTUK MENURUNKAN MAKESPAN PADA PEMBUATAN RODA GIGI
Abstract: Flow shop is the
process of determining the sequence of jobs that have the same product path.
While the flow-shop scheduling takes assumption that a number of jobs that each
has the same machine work sequence. The problems faced by com-panies, namely
the high demand and yet the existence of a good scheduling planning resulted in
the company should be able to optimize sche-duling job. One of the ways to
solve these problems is by minimizing the Makespan. This research will solve
the problem regarding to the flow shop scheduling by using cross
entropy-genetic algorithm (CEGA) method to minimize Makespan. The technique
that is used to solve the problem is by comparing the result of the application
of existing methods in the company with the proposed method (CEGA). To support
the application of CEGA used MATLAB software. Finally known that the results
CEGA can give optimal solution, Makespan values obtained for 10829 seconds. So
far, it was more effective than the method that used at the firm with Makespan
efficiency by 10.06%.
Penulis: Dian Setiya Widodo,
Mario Sarisky Dwi Ellianto
Kode Jurnal: jptindustridd150613