Abstract: The smooth process
of manufacturing and production requires the operating machine in good
condition. If the machine breakdown happened then the production process will
be stopped, the production target was not achieved, due date can not be met. So
that the costumer will become dissatisfied, and so on. The purpose of this
study is to evaluate the work system of the injection department. Also reduce
the waiting time for repair the broken machine at existing production system.
This study propose the method of modeling and simulation for examine the
working system object using the simulation software of Arena. Based on the
experiment, it can be seen that the simulation model repair in scenario 1 give
impact on the level of activity of technicians up to 20.2% without any
reduction in processing time. From the simulation model, the scenario 2
give impact of changes in the levels of
technicians activity decline by 5.56%
and can decrease the processing time up to 8.33%.
Penulis: Ong Andre Wahyu
Riyanto
Kode Jurnal: jptindustridd160200